Transmission

During FY 09 to FY 18, KE has invested c. USD 500 Million in expanding and rehabilitating its transmission network, including addition of new grid stations and transmission lines. As of June 30, 2018, KE’s transmission system comprises of 1,254 km of 220kV, 132kV and 66kV lines, with 64 grid stations and 147 power transformers. In recent years, KE has taken major steps towards enhancing the transformation capacity and improving its reliability.

 

Capacity Enhancement/Restoration:

transmission-timeline

Installations or enhancements of power transformers were carried at various locations to improve the load profile

30 MVA

Hospital Grid

July 2014

40 MVA

Malir Grid

December 2014

40 MVA

Hub Chowki Grid

December 2014

20 MVA

Agha Khan 1 & 2

March 2015

40 MVA

Clifton Grid

March 2015

40 MVA

Surjani Grid

April 2015

40 MVA

Clifton Grid

July 2015

40 MVA

Federal B Grid

September 2015

40 MVA

Gizri Grid

September 2015

40 MVA

West Wharf Grid

September 2015

40 MVA

Qayumabad Grid

October 2015

40 MVA

Dhabeji Grid

November 2015

40 MVA

Site

January 2016

40 MVA

Port Qasim

February 2016

40 MVA

KDA

February 2016

40 MVA

BOC

February 2016

40 MVA

KORANGI TOWN

March 2016

30 MVA

KORANGI EAST

April 2016

40 MVA

LIAQUATABAD

May 2016

40 MVA

LANDHI

May 2016

40 MVA

GULSHAN

May 2016

30 MVA

GARDEN

June 2016

35 MVA

RECP

June 2016

40 MVA

AGHA KHAN

July 2016

40 MVA

HOSPITAL

August 2016

40 MVA

JACOBLINE

September 2016

35 MVA

LYARI

October 2016

40 MVA

ORANGI

October 2016

40 MVA

SURJANI

December 2016

30 MVA

KDA

July 2017

40 MVA

DEFENCE

August 2017

20 MVA

GHARO

November 2017

40 MVA

SURJANI

December 2017

40 MVA

JACOBLINE

February 2018

40 MVA

HOSPITAL

February 2018

40 MVA

RECP

March 2018

40 MVA

MAYMAR

March 2018

40 MVA

LANDHI

April 2018

40 MVA

VALIKA

April 2018

40 MVA

ORANGI

April 2018

20 MVA

PIPRI EAST

April 2018

40 MVA

GULISTAN-E-JOHAR

June 2018

40 MVA

KEPZ

July 2018

40 MVA

SURJANI

August 2018

Upto June 30, 2018, 617 11kV switch installations/replacements have been carried out since July 2014 across various grid stations, as part of a comprehensive effort to ensure optimal performance.

ISO 9001:2015 QMS Certification:

The following Transmission network departments are certified under ISO 9001:2015 Quality Management System:

  • Project Implementation
  • Grid System Maintenance
  • System Operation
  • SCADA Maintenance

TP-1000:

To cater the growth in demand and service additional capacity, KE is committed on further upgrading, enhancing and expanding its transmission infrastructure.

TP-1000 is a c. USD 450 Million transmission enhancement project which will add over 1,000 MVAs to our network, enabling the utility to transmit additional c. 800 MW while improving power reliability and voltage stability. The project will include new grid stations and the addition of a Disaster Recovery Center.

The Company completed a major part of the civil and electrical design during FY 2017. Further, the transmission line design for the major material has been approved, and type tests for the 220kV and 132kV cables have been carried out. To date, 4 grid stations and 21 power trafos have been added under the TP-1000 project and the project is on course for a successful completion by the end of 2nd quarter of FY 2020.

WordPress Lightbox