During FY 09 to FY 18, KE has invested c. USD 500 Million in expanding and rehabilitating its transmission network, including addition of new grid stations and transmission lines. As of June 30, 2018, KE’s transmission system comprises of 1,254 km of 220kV, 132kV and 66kV lines, with 64 grid stations and 147 power transformers. In recent years, KE has taken major steps towards enhancing the transformation capacity and improving its reliability.
Capacity Enhancement/Restoration:

Installations or enhancements of power transformers were carried at various locations to improve the load profile
30 MVA
Hospital Grid
July 2014
40 MVA
Malir Grid
December 2014
40 MVA
Hub Chowki Grid
December 2014
20 MVA
Agha Khan 1 & 2
March 2015
40 MVA
Clifton Grid
March 2015
40 MVA
Surjani Grid
April 2015
40 MVA
Clifton Grid
July 2015
40 MVA
Federal B Grid
September 2015
40 MVA
Gizri Grid
September 2015
40 MVA
West Wharf Grid
September 2015
40 MVA
Qayumabad Grid
October 2015
40 MVA
Dhabeji Grid
November 2015
40 MVA
Site
January 2016
40 MVA
Port Qasim
February 2016
40 MVA
KDA
February 2016
40 MVA
BOC
February 2016
40 MVA
KORANGI TOWN
March 2016
30 MVA
KORANGI EAST
April 2016
40 MVA
LIAQUATABAD
May 2016
40 MVA
LANDHI
May 2016
40 MVA
GULSHAN
May 2016
30 MVA
GARDEN
June 2016
35 MVA
RECP
June 2016
40 MVA
AGHA KHAN
July 2016
40 MVA
HOSPITAL
August 2016
40 MVA
JACOBLINE
September 2016
35 MVA
LYARI
October 2016
40 MVA
ORANGI
October 2016
40 MVA
SURJANI
December 2016
30 MVA
KDA
July 2017
40 MVA
DEFENCE
August 2017
20 MVA
GHARO
November 2017
40 MVA
SURJANI
December 2017
40 MVA
JACOBLINE
February 2018
40 MVA
HOSPITAL
February 2018
40 MVA
RECP
March 2018
40 MVA
MAYMAR
March 2018
40 MVA
LANDHI
April 2018
40 MVA
VALIKA
April 2018
40 MVA
ORANGI
April 2018
20 MVA
PIPRI EAST
April 2018
40 MVA
GULISTAN-E-JOHAR
June 2018
40 MVA
KEPZ
July 2018
40 MVA
SURJANI
August 2018
Upto June 30, 2018, 617 11kV switch installations/replacements have been carried out since July 2014 across various grid stations, as part of a comprehensive effort to ensure optimal performance.
ISO 9001:2015 QMS Certification:
The following Transmission network departments are certified under ISO 9001:2015 Quality Management System:
- Project Implementation
- Grid System Maintenance
- System Operation
- SCADA Maintenance
TP-1000:
To cater the growth in demand and service additional capacity, KE is committed on further upgrading, enhancing and expanding its transmission infrastructure.
TP-1000 is a c. USD 450 Million transmission enhancement project which will add over 1,000 MVAs to our network, enabling the utility to transmit additional c. 800 MW while improving power reliability and voltage stability. The project will include new grid stations and the addition of a Disaster Recovery Center.
The Company completed a major part of the civil and electrical design during FY 2017. Further, the transmission line design for the major material has been approved, and type tests for the 220kV and 132kV cables have been carried out. To date, 4 grid stations and 21 power trafos have been added under the TP-1000 project and the project is on course for a successful completion by the end of 2nd quarter of FY 2020.